Electrical Work (Setonix)

Scheduled Maintenance Report for Pawsey Supercomputing Research Centre

Completed

The scheduled maintenance has been completed.
Posted Jul 23, 2024 - 17:12 AWST

Update

We will be undergoing scheduled maintenance during this time.
Posted Jul 19, 2024 - 08:49 AWST

Scheduled

CBIS contractors have identified during their thermographic and ultrasonic testing in the SC Cell underfloor that an isolator has a hot spot.

The isolator and cabling terminations are in need of urgent isolation and replacement, so the Setonix cabinet attached to the isolator is currently being drained. This will be the highmem partition is not available, and the work partition has reduced capacity.
Posted Jul 19, 2024 - 08:49 AWST
This scheduled maintenance affected: Setonix (Setonix work partition, Setonix highmem partition).